Project Status
2nd Quarter 2015 Status
Facilities is compiling the bid documents and they should be ready by the end of September.
The Courthouse Fire Alarm System Investigation has uncovered several shortfalls with the existing system. Facilities is compiling the updated requirements and will be submitting the new requirements for the 2017 budget.
3rd Quarter 2015 Status
Bids are scheduled to open on November 10, 2015.
4th Quarter 2015 Status
Bid Documents were opened and have been awarded to Hytech Roofing, Inc. Contracts have been written and scheduling is the next step in the process.
1st Quarter 2016 Status Project has been on hold the first quarter due to inclement weather for roof removal, expecting scheduling during 2nd Quarter.