Project Update November 4, 2019
Iverson Earth Works has completed installing the large outfall pipe and rock pad by the pond off of Pt. Whitehorn Rd, as well as a large manhole installation along Pt. Whitehorn Rd. Approximately 500 feet of storm pipe remain to be installed along Birch Bay Drive this week of November 11, 2019, with the project being substantially complete the week of November 18, 2019, weather dependent.